Northwest Water Reservoir

Northwest Water Reservoir

The Northwest Water Reservoir was made possible with a combined federal and provincial investment of $4.8 million. Our contribution to this massive infrastructure project required:

  • Large pours
  • Negotiating a small work site on a mountain-side location
  • Xypex waterproofing

We worked on the Northwest Water Reservoir between July 1, 2010 and October 31, 2010. In addition to our operators, we had personnel on site for testing, and directing traffic. We were able to overcome the logistical difficulties of the small, mountain-side location, and deliver large pours that included Xypex crystalline technology for waterproofing.


Client:

City of Fernie

Location:

Fernie, BC

Date of completion:

October 31, 2010

Duration of project:

4 months

Specialty conditions:

Challenging location

Total volume of pour:

1,000 m3

Type of concrete:

35mpa and Xypex waterproofing